Pittsburgh Water

Highway Occupancy Permit Request

Jan 16, 2025
submission #3
Application Submission

Applicant Information

Name Josh Frye
Phone Number +17245138659
Email [email protected]
Is the applicant the same as the contractor? No

Contractor Information

Name Luis Guerrero
Company PJ Dick
Phone Number +14122928675
Email [email protected]

Project Information

Property Address 530 Marshall Ave, Pittsburgh PA 15214-3016
Work Summary Set traffic control for the duration of this phase as defined in PATA figure 106. Contractor to coordinate work with PWSA. Field Locate the exact locations of existing water lines. Trench area of water line work 5' in depth or depth of waterline plus room to perform work (whichever distance is greater). Terminate existing water tap and remove 5-ft of pipe from water main per detail WS-STL. Cut water lateral 5-ft from tap, cap, and abandon remaining pipe in place. Restore pavement section per PennDOT Pub , APP. C8 - Hightway Restoration Figures.
General Date Range of Work 2025-06-15 - 2025-08-15
Tap C Number From Approved Tap-in Plans e.g. C-XXXX C3191
Completed M-949C Form (see instructions for blank form) M-949C - Pressley Ridge Water HOP - 01-16-2025.pdf
Traffic Control Plan Pressley Ridge Water HOP Plan - 01-16-2024.pdf, PATA 106.pdf
Maintenance Bond

Maintenance Bond

$30,000 Maintenance Bond Maintenance Bond executed.pdf
Approved PennDOT Permit

PennDOT Permit

HOP Permit Permit-11061319.pdf